Progress Report on N86 (Tralee – Dingle Road)

Here’s a progress update on the N86 Tralee to Dingle Road, as discussed at our Dingle Electoral Area meeting of 17/11/2010. Give me a call if you have any questions. Regards, Brendan (087 652 8841)

N86 Tralee to An Daingean Road Improvement Scheme[KY-09-4743] Progress Report on 17thNovember 2010

For An Daingean Electoral Area Meeting Scheme.

The scheme has been extended at the eastern end to Camp Junction – which is thejunction of the N86 and the R560 (Connor Pass) including junction improvements at this location.

EIA Screening: Ryan Hanley WSP have submitted final Screening Report recommends that an EIS is required for the scheme. Recommendation has been issued to An Bord Pleanala.

Preliminary Ground Investigation: IGSL commenced works on site on 13thSeptember 2010. Works scheduled to be complete by 10thDecember 2010

EIS RPS Consulting Engineers (Cork) commenced work on 3rdSeptember 2010. Currently undertaking fieldwork/baseline surveys.

Alignment/ Design: Preliminary alignment will be finalized in December, following which, it will bemade available to the public.EIS/CPO EIS/CPO to be published in June 2011 Annascaul to Gortbreagoge It is proposed to advance a 4km section of scheme between Annascaul and Gortbreagoge to construction in 2011. Part 8 will be initiated in March 2011, withconstruction commencing in August 2011. It is proposed to acquire lands byagreement and initial discussions have commenced in this regard.